Florida Lien Law Punchlist for Private Projects
NOTICE REQUIREMENTS
- Any party (except wage laborers) who do not have a direct contract with the property owner must serve a Notice to Owner within the earlier of (a) 45 days of first furnishing services or materials; or (b) 45 days from when work begins on making specialty materials; or (c) 45 days before owner’s final payment to prime contractor. Notice must be served on the owner, and all other parties “up the chain.”
- If a payment bond is posted on the project, must deliver a Notice to Contractor / Notice to Owner to the owner and general contractor within 45 days of first furnishing labor and/or materials. If later unpaid for work, lienor must serve contractor and bonding company with Notice of Nonpayment within 90 days of final furnishing of labor and/or materials to perfect rights to make claim against bond.
ABOUT NOTICE OF COMMENCEMENT & PAYMENT BONDS
-
Owner must record a Notice of Commencement before work is performed at the property, and display it at the jobsite! This notice will have important information on it for potential lien claimants.
-
If the Owner recorded a payment bond along with its Notice of Commencement, the property may not be lienable. Instead, the claimant should bring a suit against the bond.
- If bond is recorded and lien may not be possible, this does not relieve contractors from delivering a Notice to Owner.
THE MECHANICS LIEN
- Referred to as “Claim of Lien”
- Must be recorded within 90 days of last furnishing labor and/or materials. It must be served on the owner within 15 days of being recorded.
- Action to enforce the lien must be instituted within 1 year from the filing of the lien, unless action is taken by another party to shorten the period. Then, according to the action.
THE PAYMENT BOND
- If Payment Bond was recorded by the Owner/Contractor, no one has right to lien the property. Instead, the lienor can file a claim against the payment bond itself.
- Lienor must file suit against bonding company and/or bond principal within 1 year from its final furnishing of labor and/or materials. Also, note notice requirements above.

